Exercise set
Wastewater Biological Treatment Load, SRT, and Aeration Exercises
Solved wastewater biological-treatment exercises for BOD load, HRT, F/M, SRT, wasting, oxygen demand, aeration margin, sludge yield and release gates.
These exercises focus on the biological-treatment barrier in wastewater plants. They cover pollutant load, hydraulic residence time, food-to-microorganism ratio, solids retention time, mixed-liquor inventory, waste activated sludge, oxygen demand, aeration transfer, dissolved-oxygen evidence, temperature guard, blower power, sludge yield and process release gates.
Assume simplified screening calculations unless an exercise states otherwise. Field release requires flow data, composite sampling, lab QA, MLSS and MLVSS records, aeration status, dissolved-oxygen probes, sludge wasting logs, recycle flows, temperature history and effluent monitoring.
Release Evidence Notes
Biological-treatment evidence should keep load, biomass and oxygen on the same time basis. A plant can have enough tank volume but too little active biomass, enough air capacity but poor transfer, or acceptable average BOD removal while failing during cold or wet-weather conditions.
SRT evidence should include solids inventory and actual wasting. A target SRT is not real unless MLSS, tank volume, WAS flow, WAS concentration and effluent solids losses reconcile.
Aeration evidence should connect required oxygen, delivered oxygen, blower status, diffuser condition, DO sensor calibration and basin profile. A running blower does not prove oxygen transfer.
Engineering Boundary Notes
These calculations do not replace activated-sludge modeling, nitrification design, process-control testing, lab QA, permit reporting or operator certification. They are screening exercises for biological treatment release.
Common Release Mistakes
- calculating BOD load from average flow when peak wet-weather load controls the basin;
- using MLSS as if all solids were active biomass;
- changing wasting before confirming current SRT and sludge age;
- judging aeration from blower status rather than oxygen transfer and DO profile;
- combining biology, clarification and disinfection into one generic treatment margin.
Scenario Map
| Scenario | Exercises | Primary check | Engineering decision |
|---|---|---|---|
| Load and volume | 1, 2, 3, 4 | BOD/COD load, HRT and F/M ratio | Decide whether the basin loading basis is credible. |
| Biomass and wasting | 5, 6, 7, 12, 14 | SRT, WAS, inventory, temperature guard and sludge yield | Decide whether solids control supports treatment. |
| Oxygen and monitoring | 8, 9, 10, 11, 13, 16, 17 | oxygen demand, transfer margin, DO evidence, alkalinity, blower power and monitoring | Decide whether biological operation is releasable. |
| Release gate | 18 | all-of biological release | Decide whether biological treatment can close. |
Exercise 1: Daily BOD Load
Influent flow is 8200\ \text{m}^3/\text{d} and influent BOD is 185\ \text{mg/L}. Calculate daily BOD load.
Solution
Use 1\ \text{mg/L}=1\ \text{g/m}^3:
Engineering Comment
This load is the starting point for aeration, sludge production and process capacity checks.
Plausibility Check
Thousands of cubic meters per day at hundreds of milligrams per liter should produce tonnes per day of BOD load.
Exercise 2: COD-to-BOD Load Screen
Influent COD is 420\ \text{mg/L} at the same flow of 8200\ \text{m}^3/\text{d}. Compute COD load and COD:BOD load ratio using the BOD load from Exercise 1.
Solution
Engineering Comment
The ratio is a biodegradability screen. A high or drifting ratio can signal industrial load, toxicity or weak biological availability.
Plausibility Check
COD is a little more than twice BOD, so the load ratio should also be a little above two.
Exercise 3: Aeration Basin Hydraulic Residence Time
Aeration basin volume is 3100\ \text{m}^3 and flow is 8200\ \text{m}^3/\text{d}. Compute hydraulic residence time.
Solution
Engineering Comment
HRT is hydraulic exposure time, not biological age. SRT must be checked separately.
Plausibility Check
A basin volume a little over one third of daily flow gives a little over one third of a day.
Exercise 4: Food-to-Microorganism Ratio
Aeration volume is 3100\ \text{m}^3, MLVSS is 2400\ \text{mg/L} and BOD load is 1517\ \text{kg/d}. Compute F/M ratio.
Solution
Biomass mass:
F/M:
Engineering Comment
F/M helps interpret loading state, but it should be used with SRT, oxygen and settling evidence.
Plausibility Check
A tonne-scale daily load over several tonnes of biomass should give a fraction per day.
Exercise 5: Solids Retention Time
Total solids inventory in aeration and clarifiers is 9200\ \text{kg}. WAS solids removed are 720\ \text{kg/d} and effluent solids loss is 80\ \text{kg/d}. Compute SRT.
Solution
Engineering Comment
Effluent solids loss is part of the SRT denominator. Ignoring it overstates sludge age during washout.
Plausibility Check
Losing about 800\ \text{kg/d} from a 9200\ \text{kg} inventory gives a little over eleven days.
Exercise 6: WAS Rate for Target SRT
Target SRT is 10\ \text{d}. Solids inventory is 9200\ \text{kg} and effluent solids loss is 80\ \text{kg/d}. Compute required WAS solids removal.
Solution
Total required solids removal:
WAS solids:
Engineering Comment
The wasting target should be converted to a WAS flow using measured WAS concentration.
Plausibility Check
Shortening SRT from 11.5 to 10 days requires removing more solids each day.
Exercise 7: WAS Flow From Solids Concentration
Required WAS solids removal is 840\ \text{kg/d}. WAS concentration is 7800\ \text{mg/L}. Compute WAS flow.
Solution
Convert concentration:
Flow:
Engineering Comment
WAS concentration drift changes the real wasting mass even if the pump flow setpoint is unchanged.
Plausibility Check
At about 8\ \text{kg/m}^3, moving roughly 100\ \text{m}^3/\text{d} removes roughly 800\ \text{kg/d}.
Exercise 8: Carbonaceous Oxygen Demand
Assume 1.1\ \text{kg O}_2 is required per kg of BOD removed. BOD load is 1517\ \text{kg/d} and removal is 92\%. Compute oxygen demand.
Solution
Removed BOD:
Oxygen demand:
Engineering Comment
This covers carbonaceous demand only. Nitrification, endogenous respiration and process factors can add demand.
Plausibility Check
Oxygen demand near the removed BOD load is expected for carbon oxidation.
Exercise 9: Aeration Transfer Margin
Required oxygen is 1536\ \text{kg/d}. Field oxygen transfer capacity is 1880\ \text{kg/d}. Compute aeration margin.
Solution
Engineering Comment
A 22.4\% margin can disappear with diffuser fouling, warm water, altitude correction or higher ammonia load.
Plausibility Check
The spare capacity is about 340\ \text{kg/d} over a 1500\ \text{kg/d} requirement, so about one fifth is plausible.
Exercise 10: Dissolved-Oxygen Evidence Gate
Four basin zones have calibrated DO readings of 1.8, 2.1, 2.4 and 0.9\ \text{mg/L}. The operating floor is 1.5\ \text{mg/L}. Decide whether the DO profile passes.
Solution
The minimum reading is:
Since:
the profile fails.
Engineering Comment
Average DO would hide the oxygen-deficient zone. Release should use the limiting profile.
Plausibility Check
One zone is visibly below the operating floor, so the gate cannot pass.
Exercise 11: Alkalinity Demand Screen
Nitrification removes 210\ \text{kg/d} as nitrogen. Use 7.14\ \text{kg alkalinity as CaCO3} per kg N. Compute alkalinity consumed.
Solution
Engineering Comment
Alkalinity demand links biological treatment to pH stability. Low alkalinity can reduce nitrification even when oxygen is adequate.
Plausibility Check
The factor is about seven, so 210\ \text{kg/d} N creates about 1500\ \text{kg/d} alkalinity demand.
Exercise 12: Cold-Weather SRT Guard
Cold-weather operating guidance requires SRT above 14\ \text{d}. Current SRT is 11.5\ \text{d}. Compute shortfall.
Solution
Engineering Comment
The response may be reduced wasting, more solids inventory or load reduction, but clarifier capacity must be checked before increasing MLSS.
Plausibility Check
The plant is a few days below the cold-weather target.
Exercise 13: Blower Power Screen
Total blower power is 185\ \text{kW} while delivering 1880\ \text{kg O}_2/\text{d}. Compute specific energy in \text{kWh/kg O}_2.
Solution
Daily energy:
Specific energy:
Engineering Comment
Specific energy is not a release gate alone, but rising values can reveal diffuser fouling or control instability.
Plausibility Check
Thousands of kWh per day over thousands of kilograms oxygen per day gives a few kWh per kilogram.
Exercise 14: Sludge Yield Estimate
BOD removed is 1396\ \text{kg/d} and observed sludge yield is 0.55\ \text{kg TSS/kg BOD removed}. Estimate waste sludge production.
Solution
Engineering Comment
The yield estimate should be compared with actual WAS and effluent solids. A mismatch indicates inventory change or measurement error.
Plausibility Check
Yield near one half of removed BOD gives several hundred kilograms per day.
Exercise 15: Effluent BOD Mass Limit
Permit limit is 25\ \text{mg/L} BOD as a daily concentration at 8200\ \text{m}^3/\text{d}. Compute equivalent daily mass limit.
Solution
Engineering Comment
Mass and concentration limits should both be checked when flows vary.
Plausibility Check
The limit concentration is much lower than influent concentration, so the allowed load is much lower than influent load.
Exercise 16: Monitoring Completion Score
The biological release package requires BOD composite, COD check, MLSS, MLVSS, WAS concentration, DO profile, blower status, temperature, pH and effluent BOD. Eight of ten records are complete. Compute completion.
Solution
Engineering Comment
Completion is not enough if missing records are DO profile or effluent BOD, because those are direct release barriers.
Plausibility Check
Eight out of ten records is exactly 80\%.
Exercise 17: Process Stability Score
Assign one point each for SRT above target, aeration margin above 15\%, DO profile passing, pH in range and evidence completion above 90\%. Current status: SRT fails, aeration margin passes, DO fails, pH passes and evidence completion fails. Compute score.
Solution
Passing items are aeration margin and pH:
Engineering Comment
The score shows why a single good aeration margin cannot release the biological process.
Plausibility Check
Two passing checks out of five is less than half.
Exercise 18: Biological Treatment Release Gate
A release gate requires SRT at least 14\ \text{d}, aeration margin above 15\%, DO profile passing, effluent BOD load below 205\ \text{kg/d} and monitoring completion above 90\%. Current values are SRT 11.5\ \text{d}, aeration margin 22.4\%, DO profile fail, effluent BOD load 180\ \text{kg/d} and completion 80\%. Decide release status.
Solution
Aeration margin passes and effluent load passes. SRT, DO profile and evidence completion fail:
Release status:
Engineering Comment
The plant should hold biological release until sludge age, oxygen profile and evidence records are corrected.
Plausibility Check
An all-of biological gate fails when three required controls fail.
Validation Package Checklist
- Flow, BOD, COD, biomass, wasting and effluent loads use the same operating window.
- SRT includes solids inventory, WAS solids and effluent solids losses.
- Aeration evidence includes required oxygen, delivered oxygen, DO profile, blower state and sensor calibration.
- Release decisions separate biological treatment from clarifier and disinfection barriers.