Exercise set
Water and Wastewater Pump Station Duty, Power, NPSH, and VFD Exercises
Solved pump-station exercises for duty point, pump power, static head, curve margin, NPSH, motor current, VFD speed and release gates.
These exercises practise water and wastewater pump-station hydraulic duty decisions: flow conversion, pump input power, static head, total dynamic head, pump curve margin, NPSH, motor current, VFD speed, affinity laws, wet-well drawdown and pump acceptance gates.
The goal is to verify the installed operating point, not nameplate capacity. A pump can have enough nominal flow and still fail because head is higher than assumed, wet-well level drops, NPSH margin is low, VFD speed is limited or motor current approaches its guard.
Assume water density unless stated otherwise. Field release should use installed pump curves, measured wet-well levels, pressure logs, current readings, VFD parameters, valve positions and acceptance-test records.
Release Evidence Notes
Pump evidence should identify flow, total dynamic head, speed, impeller condition, wet-well level and motor current at the same operating point.
Power evidence should separate hydraulic power from input power. Efficiency, motor efficiency and VFD losses should be visible when energy or electrical margin matters.
NPSH evidence should use worst credible suction condition: low wet-well level, warm liquid, high flow and known suction losses.
VFD evidence should show minimum speed limits, self-cleansing velocity, cooling constraints, pressure control and current limits.
Engineering Boundary Notes
This page covers pump duty and power. Pipe headloss, valves and surge transients belong in the pipe/transient exercise set. Standby availability, runtime balance, leakage trend and release checklist closure belong in the reliability exercise set.
Scenario Map
| Scenario | Exercises | Primary check | Engineering decision |
|---|---|---|---|
| Pump duty point | 1-5 | flow, area, velocity, static head and TDH | Confirm the duty point used for selection. |
| Power and efficiency | 6-9 | hydraulic power, input power, energy and current | Check motor, VFD and energy margin. |
| NPSH and operating envelope | 10-14 | suction margin, wet-well drawdown and speed change | Decide whether operating limits are acceptable. |
| Pump release | 15-18 | curve margin, guarded current and acceptance gates | Release, restrict or retest the pump station. |
Exercise 1: Flow Conversion
A pump station flow is:
Convert to cubic meters per second.
Solution
Use:
Thus:
Engineering Comment
Consistent units prevent large pump-power and velocity errors.
Plausibility Check
One thousand liters make one cubic meter, so tens of liters per second are hundredths of a cubic meter per second.
Exercise 2: Pipe Area at Pump Discharge
Discharge pipe diameter is:
Find cross-sectional area.
Solution
Area:
Engineering Comment
Area is needed before checking discharge velocity and system curve.
Plausibility Check
A 300 mm pipe has an area a little above 0.07\ \text{m}^2.
Exercise 3: Pump Discharge Velocity
Flow is:
Area is:
Find velocity.
Solution
Velocity:
Engineering Comment
Velocity should be checked against self-cleansing, headloss, abrasion, odor and surge criteria.
Plausibility Check
About 0.08\ \text{m}^3/\text{s} in a 300 mm pipe gives velocity close to one meter per second.
Exercise 4: Static Head from Level Difference
Discharge hydraulic grade is:
Wet-well operating level is:
Find static head.
Solution
Static head:
Engineering Comment
Wet-well level changes can move the pump duty point during a run.
Plausibility Check
The discharge grade is about twenty-five meters above wet-well level.
Exercise 5: Total Dynamic Head
Static head is:
Pipe friction loss is:
Minor losses are:
Find TDH.
Solution
Total dynamic head:
Engineering Comment
Pump acceptance should verify flow at this total dynamic head, not at zero static lift.
Plausibility Check
The terms sum directly to a TDH in the mid-forties.
Exercise 6: Hydraulic Power
A pump delivers:
against:
Use:
Find hydraulic power.
Solution
Hydraulic power:
So:
Engineering Comment
Hydraulic power is lower than input power because pump and drive efficiency are not perfect.
Plausibility Check
Moderate flow against tens of meters of head gives tens of kilowatts.
Exercise 7: Pump Input Power
Hydraulic power is:
Pump efficiency is:
Find input power.
Solution
Input power:
Engineering Comment
Motor sizing should include motor efficiency, service factor and operating envelope.
Plausibility Check
Dividing by efficiency below one raises the required input power.
Exercise 8: Daily Energy Use
Input power is:
Daily runtime is:
Find daily energy.
Solution
Energy:
Engineering Comment
Energy evidence should be checked against pump starts, level control and wet-weather operation.
Plausibility Check
About thirty-three kilowatts for about ten hours is about three hundred kilowatt-hours.
Exercise 9: Motor Current Guard
Motor full-load current is:
Release requires measured current below 95\% of full load. Find guarded limit.
Solution
Guarded limit:
Engineering Comment
The current guard should be checked at final speed, valve position and wet-well condition.
Plausibility Check
Five percent below 62 A is just under 59 A.
Exercise 10: Motor Current Status
Guarded current limit is:
Measured current is:
Check status.
Solution
Since:
the current gate passes.
Engineering Comment
A pass is valid only for the tested hydraulic duty point.
Plausibility Check
Measured current is below the guard by 1.9 A.
Exercise 11: Wet-Well Drawdown Head Increase
Wet-well level drops by:
Find static-head increase and pressure equivalent.
Solution
Head increase:
Pressure:
Engineering Comment
Pump margin should be checked at the lowest allowed wet-well level.
Plausibility Check
Each meter of water is about 9.8 kPa, so 2.4 m is about 24 kPa.
Exercise 12: NPSH Margin
Available NPSH is:
Required NPSH is:
Find margin.
Solution
Margin:
Engineering Comment
NPSH should be reviewed at maximum flow and worst suction condition.
Plausibility Check
Available NPSH exceeds required NPSH by more than one meter.
Exercise 13: NPSH Release Gate
NPSH margin is:
The release rule requires:
Check release.
Solution
Since:
the NPSH gate passes.
Engineering Comment
The pass does not cover future fouling or lower wet-well levels unless those were included.
Plausibility Check
The margin exceeds the rule by 0.4 m.
Exercise 14: VFD Speed Flow Estimate
Full-speed flow is:
VFD speed is:
Estimate flow.
Solution
Using affinity law:
Engineering Comment
System curve and minimum velocity may limit actual speed reduction.
Plausibility Check
Flow scales approximately linearly with speed.
Exercise 15: VFD Head Estimate
Full-speed head is:
Speed is:
Estimate pump head by affinity law.
Solution
Head scales with speed squared:
Engineering Comment
The pump may not meet static head at reduced speed if the system requires more head.
Plausibility Check
Head falls faster than flow because of the squared speed relation.
Exercise 16: Pump Curve Flow Margin
Required flow is:
Pump curve gives:
at measured head. Find margin.
Solution
Margin:
Percentage:
Engineering Comment
Impeller wear, valve throttling or higher roughness can consume a ten-percent margin.
Plausibility Check
The pump is slightly above required duty, so margin near ten percent is reasonable.
Exercise 17: Minimum Flow Gate
Minimum continuous stable flow is:
VFD low-speed operation produces:
Check gate.
Solution
Since:
the low-speed setting fails the minimum-flow gate.
Engineering Comment
Running below minimum stable flow can cause heating, vibration or recirculation damage.
Plausibility Check
The operating flow is three liters per second below the minimum.
Exercise 18: Pump Duty Release Gate
A pump acceptance package has:
| Gate | Requirement | Current result |
|---|---|---|
| curve flow margin | at least 8\% | 10.3\% |
| motor current | below guarded limit | pass |
| NPSH margin | at least 1.0 m | 1.4 m |
| minimum VFD flow | at least 35 L/s | 32 L/s |
Decide whether to release.
Solution
Curve, current and NPSH gates pass. Minimum VFD flow fails:
The pump duty package is not releasable without a speed limit or revised operating rule.
Engineering Comment
An acceptable full-duty point does not prove that all VFD operating modes are safe.
Plausibility Check
One hard gate fails, so the release must be held or restricted.
Validation Package Checklist
A strong pump-station duty solution should check:
- whether flow, head, speed and current are measured at the same duty point;
- whether wet-well level and static head represent the worst operating case;
- whether pump curve margin includes wear and valve condition;
- whether input power includes efficiency assumptions;
- whether NPSH margin uses worst suction condition;
- whether VFD low-speed operation meets minimum-flow and velocity limits;
- whether acceptance gates are all closed before release.
Common Release Mistakes
Common mistakes include using nameplate flow instead of installed duty, checking pump power with mixed units, ignoring wet-well drawdown, accepting VFD speed reduction without minimum-flow review, checking NPSH only at nominal conditions, treating current margin as hydraulic margin, and releasing the pump because full-speed duty passes while low-speed operation fails.