Exercise set
Gas Absorption, Stripping, and Adsorption Separation Exercises
Solved gas-separation exercises for absorber removal, solvent circulation, stripping, equilibrium margin, adsorber capacity, breakthrough and release gates.
These exercises focus on gas-contacting separations: absorption, stripping and adsorption. They cover contaminant removal, outlet load, solvent circulation, equilibrium margin, transfer height, pressure-drop margin, stripping duty, adsorbent capacity, breakthrough service time, regeneration flow and release evidence.
Assume simplified screening calculations unless an exercise states otherwise. Real design must check thermodynamic model, gas composition, temperature, pressure, packing or tray hydraulics, foaming, solvent degradation, adsorbent aging, fire and toxicity hazards, emissions monitoring and interlock state.
Release Evidence Notes
Gas-separation evidence must preserve inlet load, outlet load, removal efficiency and operating envelope. A high percent removal is not enough if the residual emission load exceeds the permit or downstream process limit.
Absorption and stripping evidence should include solvent rate, solvent condition, equilibrium approach, temperature, pressure, flooding margin, pressure drop and sample basis.
Adsorption evidence should include bed inventory, working capacity, breakthrough criterion, humidity or poisoning risk, regeneration status, bypass position and analyzer proof.
Engineering Boundary Notes
These calculations do not replace rigorous rate-based column design, vendor adsorption curves, hazardous-area review, relief design, emissions certification or operator procedures. They are release and design-screen exercises.
Common Release Mistakes
- reporting percent removal without outlet load or permit margin;
- using clean solvent capacity after solvent has accumulated contaminant;
- ignoring pressure drop, flooding and foaming in packed absorbers;
- extending adsorber service from ideal capacity while breakthrough data are missing;
- treating bypass or standby-bed alignment as an operator note instead of a release gate.
Scenario Map
| Scenario | Exercises | Primary check | Engineering decision |
|---|---|---|---|
| Absorption removal | 1, 2, 3, 4, 5, 8, 9 | load, solvent circulation, transfer and equilibrium | Decide whether absorber performance is credible. |
| Stripping service | 6, 7, 10 | stripping flow, removal and heat load | Decide whether regeneration or stripping can support operation. |
| Adsorption service | 11, 12, 13, 14, 15 | capacity, breakthrough, utilization, regeneration and standby | Decide whether adsorber operation can continue. |
| Release gate | 16, 17, 18 | emissions closure, evidence and all-of gate | Decide whether the gas-separation package can close. |
Exercise 1: Absorber Contaminant Removal
A gas stream contains 120\ \text{kg/h} of contaminant. The absorber removes 88\%. Compute outlet contaminant load.
Solution
Engineering Comment
Removal fraction should be tied to solvent condition, gas rate, temperature and sampling location.
Plausibility Check
Twelve percent of one hundred twenty kilograms per hour remains.
Exercise 2: Outlet Load Permit Margin
Outlet load is 14.4\ \text{kg/h} and the permitted maximum is 18.0\ \text{kg/h}. Compute margin.
Solution
Engineering Comment
A positive margin can still be weak if analyzer uncertainty, feed spikes or solvent degradation are large.
Plausibility Check
The outlet is 3.6\ \text{kg/h} below an 18\ \text{kg/h} limit, one fifth of the limit.
Exercise 3: Solvent Circulation From L/G Ratio
Gas flow is 9500\ \text{kg/h}. Target solvent-to-gas mass ratio is 1.8. Compute solvent circulation.
Solution
Engineering Comment
The circulation target is useful only if the pump, distributor and solvent quality can maintain it.
Plausibility Check
The solvent rate should be a little less than twice the gas mass rate.
Exercise 4: Absorbent Circulation Volume
Solvent circulation is 17100\ \text{kg/h} and solvent density is 1020\ \text{kg/m}^3. Compute volumetric circulation.
Solution
Engineering Comment
Pump curves and distributor wetting should be checked at the volumetric rate, not only mass rate.
Plausibility Check
A density near water makes tonnes per hour numerically similar to cubic meters per hour.
Exercise 5: Packed-Bed Pressure Drop Margin
Measured packed-bed pressure drop is 2.9\ \text{kPa} and the high-pressure-drop action level is 4.0\ \text{kPa}. Compute margin.
Solution
Engineering Comment
Pressure drop trend can reveal fouling, flooding, foaming or liquid maldistribution before outlet concentration rises.
Plausibility Check
The measured value is below but not far from the action level, so the margin is moderate.
Exercise 6: Stripping Gas Requirement
A stripper treats 6.5\ \text{m}^3/\text{h} of liquid. Required stripping gas ratio is 28\ \text{m}^3 gas per \text{m}^3 liquid. Compute gas flow.
Solution
Engineering Comment
The ratio should be checked against off-gas treatment capacity and vapor flammability.
Plausibility Check
Tens of gas volumes per liquid volume over several cubic meters per hour gives hundreds of cubic meters per hour.
Exercise 7: Stripping Removal
Liquid contaminant load entering a stripper is 42\ \text{kg/h} and stripping removes 76\%. Compute remaining liquid contaminant load.
Solution
Engineering Comment
The stripped contaminant becomes an off-gas or condensate load; it must appear somewhere in the release package.
Plausibility Check
About one quarter of forty-two kilograms per hour remains.
Exercise 8: Equilibrium Approach Screen
For a dilute absorber, equilibrium gas fraction at the outlet liquid condition is y^*=0.012. Measured outlet gas fraction is y=0.018. Compute approach ratio y/y^*.
Solution
Engineering Comment
The outlet gas is above equilibrium. The ratio is a screen for contact limitation or insufficient solvent rate.
Plausibility Check
The measured fraction is fifty percent higher than equilibrium, so the ratio is 1.5.
Exercise 9: Solvent Loading Capacity
Lean solvent can accept 0.045\ \text{kg contaminant/kg solvent} before the release limit is threatened. Solvent flow is 17100\ \text{kg/h}. Compute contaminant capacity.
Solution
Engineering Comment
Working capacity should be corrected for lean loading, degradation, temperature and foaming risk.
Plausibility Check
Five percent of about seventeen thousand kilograms per hour is about eight hundred kilograms per hour.
Exercise 10: Stripper Reboiler Heat Screen
A solvent regenerator evaporates 1250\ \text{kg/h} of stripping vapor. Latent heat is 2250\ \text{kJ/kg}. Estimate heat duty.
Solution
Engineering Comment
Regeneration heat can become the utility constraint that limits absorber operation.
Plausibility Check
Thousands of kilograms per hour times thousands of kilojoules per kilogram gives megajoules per hour and hundreds of kilowatts.
Exercise 11: Adsorbent Working Capacity
A carbon bed contains 1800\ \text{kg} adsorbent. Working capacity is 0.12\ \text{kg contaminant/kg carbon}. Compute usable contaminant capacity.
Solution
Engineering Comment
Working capacity is lower than theoretical capacity when humidity, temperature swing or co-contaminants compete.
Plausibility Check
Twelve percent of 1800 kilograms is a few hundred kilograms.
Exercise 12: Breakthrough Service Time
Contaminant load to an adsorber is 9.0\ \text{kg/h} and usable capacity is 216\ \text{kg}. Estimate service time to breakthrough.
Solution
Engineering Comment
The service estimate should be shortened if outlet analyzer trend or humidity indicates early breakthrough.
Plausibility Check
A bed that holds a few hundred kilograms at a load of about ten kilograms per hour lasts about one day.
Exercise 13: Carbon Bed Utilization
At changeout, contaminant captured is 168\ \text{kg} and usable capacity estimate is 216\ \text{kg}. Compute utilization.
Solution
Engineering Comment
Low utilization may indicate conservative changeout, channeling, sampling uncertainty or a poor breakthrough criterion.
Plausibility Check
Captured mass is about three quarters of capacity, so utilization near 80\% is plausible.
Exercise 14: Regeneration Purge Flow
Regeneration requires 5 bed volumes of purge gas. Bed void volume is 22\ \text{m}^3 and regeneration time is 2.0\ \text{h}. Compute purge flow.
Solution
Engineering Comment
Purge flow should be checked against off-gas handling, inerting and flammability limits.
Plausibility Check
Moving about one hundred cubic meters over two hours gives a few dozen cubic meters per hour.
Exercise 15: Duty-Standby Bed Availability
Two adsorber beds are arranged duty and standby. Each bed availability is 0.94. Estimate probability that at least one bed is available, assuming independent failures.
Solution
Both unavailable:
At least one available:
Engineering Comment
Shared valves, analyzers or bypass dampers can defeat the independence assumption.
Plausibility Check
Two independent beds should be much more available than one bed.
Exercise 16: Gas-Separation Emissions Closure
An emissions closure package requires absorber outlet load, pressure drop, solvent circulation, adsorber breakthrough trend and bypass status. Four of five records are complete. Compute completion.
Solution
Engineering Comment
Missing bypass status or breakthrough trend should hold release even if outlet load is currently below limit.
Plausibility Check
Four of five is exactly eighty percent.
Exercise 17: Gas-Separation RPN
A bypass-open failure mode has severity 8, occurrence 3 and detection 4. Compute RPN.
Solution
Engineering Comment
High severity makes bypass interlocks and position proof important even when occurrence is not frequent.
Plausibility Check
Multiplying single-digit ratings should give a two- or three-digit score.
Exercise 18: Gas-Separation Release Gate
A release gate requires outlet load below 18\ \text{kg/h}, pressure-drop margin above 20\%, adsorber service time above 20\ \text{h}, no bypass and evidence completion above 90\%. Current values are 14.4\ \text{kg/h}, 27.5\%, 24.0\ \text{h}, no bypass and 80\% completion. Decide release status.
Solution
Outlet load, pressure drop, service time and bypass status pass. Evidence completion fails:
Release status:
Engineering Comment
The process may be performing, but the release package cannot close without complete operating evidence.
Plausibility Check
An all-of release gate fails when one mandatory evidence threshold fails.
Validation Package Checklist
- Inlet load, outlet load, removal efficiency and permit basis are reconciled.
- Solvent circulation, solvent condition, equilibrium approach and pressure drop are recorded.
- Adsorber capacity, breakthrough, regeneration and bypass status are documented.
- Release decisions preserve emissions, safety and interlock evidence instead of relying on percent removal alone.