Exercise set
Supplier Performance Lead Time, Disruption, and Release Evidence Exercises
Solved supplier-performance exercises for measured lead time, delivery service, outage coverage, dual sourcing, quality release and recovery gates.
These exercises practise supplier-release decisions: measured lead time, delivery promise performance, outage coverage, dual-source recovery, supplier capacity, backlog burn-down, quality release, incoming inspection, ramp readiness, expedite dependence and supplier release gates.
The goal is to decide whether a supplier can support a released plan with evidence, not promises. A supplier may meet ship date but miss production need if quality release, transport, inspection, documentation, packaging or recovery capacity fails.
Assume simplified screening data unless an exercise states otherwise. Real supplier release should also check approved source status, process change control, capacity evidence, quality history, inspection status, route risk, customs delay, alternate-source qualification, engineering deviation and shortage escalation.
Release Evidence Notes
Supplier evidence should separate quoted lead time, confirmed order date, actual ship date, delivery date, receiving timestamp and quality-release timestamp. The boundary must match the release decision.
Performance evidence should include mean, tail and on-time percentage. A supplier with acceptable average lead time can still fail because late deliveries are frequent or severe.
Disruption evidence should show available stock, alternate-source capacity, ramp timing, recovery backlog and quality approval state. Expedites are not a stable release plan unless their capacity and risk are explicit.
Supplier release should connect quantity, timing, quality and documentation. A part is not released to production until the supplied material is approved, traceable and usable at the correct revision.
Engineering Boundary Notes
This page covers supplier performance and supplier-release evidence. Inventory policy belongs in the inventory-policy exercise set. Kanban, unit load, inspection delay and line-side execution belong in the material replenishment exercise set.
If the issue is supplier-change qualification deliverables rather than recurring performance math, use the supplier-change qualification project.
Scenario Map
| Scenario | Exercises | Primary check | Engineering decision |
|---|---|---|---|
| Lead time and delivery service | 1-5 | measured lead time, on-time rate, tail delay and z margin | Use measured lead time or restrict release. |
| Disruption and recovery | 6-10 | outage coverage, alternate capacity, backlog burn-down and ramp | Approve, escalate or throttle demand. |
| Quality and release evidence | 11-15 | PPM, inspection yield, documentation closure and deviation exposure | Release, hold or requalify material. |
| Supplier gate | 16-18 | expedite dependence, capacity margin and hard gates | Release, restrict or reject supplier plan. |
Exercise 1: Mean Measured Lead Time
A supplier promises:
Measured lead times are:
Find the mean.
Solution
Mean lead time:
Engineering Comment
Planning should use measured performance until supplier recovery evidence proves the promise is reliable.
Plausibility Check
Four values exceed eight days, so the mean should exceed the promise.
Exercise 2: On-Time Delivery Rate
Using the same six deliveries, count deliveries at or below:
Find on-time percentage.
Solution
Two deliveries meet promise:
On-time rate:
Engineering Comment
The promise is not credible as a planning input. A low on-time rate should trigger recovery action or a larger planning buffer.
Plausibility Check
Only two of six meet the promised lead time, so one third is expected.
Exercise 3: Lead-Time Delay Margin
Required production need date allows:
Measured mean lead time is:
Find mean margin.
Solution
Margin:
Engineering Comment
The average margin is less than one day. Tail delivery performance and inspection delay may consume it.
Plausibility Check
The mean is slightly below the maximum, leaving a small positive margin.
Exercise 4: Lead-Time Z Screen
Measured lead time has:
Need date allows:
Find z margin.
Solution
Use:
Thus:
Engineering Comment
A z margin below one is weak for a constrained supplier. The release plan should not rely on average lead time alone.
Plausibility Check
The margin is less than one standard deviation, so z below one is expected.
Exercise 5: Late-Delivery Tail Estimate
For:
use a one-sided normal tail of:
Estimate probability of missing the need date.
Solution
The tail probability is:
Engineering Comment
Nearly one in four late deliveries is not a stable release basis for constrained production.
Plausibility Check
A z margin below one should produce a large tail probability.
Exercise 6: Supplier Outage Coverage
Quality-cleared safety stock is:
Demand is:
Supplier outage is expected to last:
Check coverage.
Solution
Outage demand:
Remaining stock:
The outage is covered.
Engineering Comment
This assumes the stock is usable and not allocated. If quality or revision status is wrong, the coverage is false.
Plausibility Check
Four weeks consumes less than the available stock.
Exercise 7: Maximum Covered Outage
Using:
find maximum covered outage duration.
Solution
Coverage duration:
Engineering Comment
The plan has only about one extra week beyond the four-week outage assumption. Monitor recovery date closely.
Plausibility Check
Seven hundred units per week consumes thirty-five hundred units in five weeks, so 5.14 weeks is plausible.
Exercise 8: Dual-Source Recovery Capacity
Normal demand is:
Primary supplier can deliver:
Alternate supplier can deliver:
after ramp. Find reserve.
Solution
Combined capacity:
Reserve:
Engineering Comment
The reserve is small. Any quality hold, transport delay or yield loss can erase recovery margin.
Plausibility Check
Combined capacity is slightly above demand, so reserve is positive but modest.
Exercise 9: Recovery Backlog Burn-Down
Supplier backlog is:
Weekly capacity above demand is:
Find recovery time.
Solution
Time:
Engineering Comment
An eight-week recovery may be too slow for a launch or shutdown window. Demand throttling or more alternate capacity may be needed.
Plausibility Check
Three hundred units per week clears twenty-four hundred units in eight weeks.
Exercise 10: Ramp Gap
Alternate supplier ramp takes:
Demand during ramp is:
Primary supplier delivers:
Find ramp-week gap.
Solution
Gap:
Engineering Comment
Steady recovery capacity after ramp does not protect the ramp week. Buffer stock or demand smoothing must cover the gap.
Plausibility Check
Primary capacity is eight hundred units below demand.
Exercise 11: Supplier Quality PPM
Incoming lots total:
Defects found:
Calculate PPM.
Solution
PPM:
Engineering Comment
PPM should be separated by defect type and severity. A low count of critical defects can still block release.
Plausibility Check
Thirty-four defects in eighty-five thousand units is four defects per ten thousand, or four hundred per million.
Exercise 12: Incoming Inspection Yield
An incoming inspection samples:
units and rejects:
Find inspection yield.
Solution
Accepted units:
Yield:
Engineering Comment
Inspection yield is not supplier process capability. It is release evidence for the inspected lots and inspection method.
Plausibility Check
Twelve rejects in four hundred is three percent rejected, so yield is ninety-seven percent.
Exercise 13: Documentation Closure
A supplier release package requires:
documents. Approved documents:
The rule requires all documents. Check release.
Solution
Closure:
The hard gate fails because:
Engineering Comment
Missing certificates, deviations or inspection plans can block release even when material is present.
Plausibility Check
One missing document makes completion high but not complete.
Exercise 14: Capacity Claim Margin
A supplier claims capacity:
Demonstrated validated capacity is:
Demand is:
Find validated reserve.
Solution
Validated reserve:
Claimed reserve would be:
Engineering Comment
Release should use demonstrated capacity, not unvalidated supplier claims.
Plausibility Check
The validated reserve is much smaller than the claimed reserve because validated capacity is lower.
Exercise 15: Deviation Exposure
A supplier deviation applies to:
units. Daily production demand is:
Find days of production exposed to the deviation.
Solution
Exposure:
Engineering Comment
Deviation release should state affected quantity, serial range, risk controls and expiry. Four production days is not negligible.
Plausibility Check
Eight hundred units per day consumes thirty-two hundred units in four days.
Exercise 16: Expedite Dependence
A recovery plan needs:
Normal validated supply is:
Expedites provide:
Find expedite share of weekly supply.
Solution
Total supply:
Expedite share:
Engineering Comment
High expedite dependence may be acceptable for a short recovery but weak for normal release.
Plausibility Check
Seven hundred out of just over five thousand is a little under fourteen percent.
Exercise 17: Supplier Risk Priority
Supplier risk scores are:
A containment action improves detection to:
Compute RPN before and after.
Solution
Before:
After:
Engineering Comment
Detection improvement helps, but occurrence remains unchanged. The supplier corrective action should address root cause, not only sorting.
Plausibility Check
Detection score drops from five to three, so RPN should fall by forty percent.
Exercise 18: Supplier Release Gate
A supplier release package has:
| Gate | Requirement | Current result |
|---|---|---|
| on-time delivery | at least 90\% | 33.3\% |
| validated capacity reserve | positive | +400 units/week |
| document closure | 100\% | 94.4\% |
| quality yield | at least 98\% | 97.0\% |
Decide whether to release.
Solution
Validated capacity passes:
Delivery, documentation and quality gates fail:
The supplier is not releasable for unrestricted production.
Engineering Comment
Supplier release requires timing, quality and documentation evidence. One positive capacity margin does not compensate for failed delivery and quality gates.
Plausibility Check
Three hard gates fail, so the release decision must be hold, restrict or escalate.
Validation Package Checklist
A strong supplier-performance solution should check:
- whether lead-time measurement uses the correct boundary;
- whether average, on-time percentage and tail risk are all visible;
- whether outage coverage uses usable stock and current demand;
- whether alternate-source capacity is approved and ramp timing is included;
- whether backlog recovery time is acceptable for the business need;
- whether quality performance separates severity and defect class;
- whether documentation and deviations are closed before release;
- whether expedite dependence is temporary, controlled and visible.
Common Release Mistakes
Common mistakes include planning from quoted lead time instead of measured release lead time, using average lead time while ignoring late-tail risk, assuming safety stock is usable without quality status, claiming dual-source recovery before ramp week is covered, using supplier capacity claims instead of demonstrated output, releasing material with incomplete documents, treating sort containment as root-cause correction, and approving a supplier because one gate passes while delivery or quality gates fail.