Exercise set
Engineering Investment NPV, Payback, IRR, and Capital Rationing Exercises
Solved engineering investment exercises for present value, NPV, payback, IRR, profitability index, capital rationing and approval gates.
These exercises practise engineering investment appraisal: present value, net present value, simple payback, discounted payback, IRR, profitability index, capital rationing, threshold savings, scenario NPV and approval gates.
The goal is to decide whether a proposed engineering investment earns its required return under stated technical assumptions. A project can pass payback but fail NPV, pass IRR but be weaker than a larger alternative, or pass finance metrics while technical evidence remains weak.
Assume the discount factors given in each exercise. Real investment approval should also check inflation basis, tax, commissioning risk, benefit evidence, operating constraints, downtime during implementation, safety gates and portfolio interactions.
Release Evidence Notes
Investment evidence should state initial cost, timing, benefits, residual value, discount rate, approval threshold and sign convention. Costs are negative and savings are positive unless stated otherwise.
NPV evidence should be preferred for value creation. Payback measures recovery speed, not total value, and IRR can be misleading for mutually exclusive or nonstandard cash flows.
Capital-rationing evidence should identify budget constraints, indivisible projects, dependencies and nonfinancial gates. A high profitability index does not override safety or reliability requirements.
Technical benefit evidence should be traceable to measured energy, throughput, quality, maintenance or downtime changes.
Engineering Boundary Notes
This page covers investment appraisal. Lifecycle cost and replacement economics belong in the lifecycle-cost exercise set. Tax, escalation and ramp-up cash-flow treatment belong in the cash-flow evidence exercise set.
Scenario Map
| Scenario | Exercises | Primary check | Engineering decision |
|---|---|---|---|
| Present value and NPV | 1-5 | discounted savings, residual value and NPV | Approve, reject or request evidence. |
| Payback and IRR | 6-9 | simple payback, discounted payback and IRR relative to MARR | Check recovery and return limits. |
| Capital rationing | 10-14 | profitability index, budget fit and threshold savings | Select portfolio under constraints. |
| Approval sensitivity | 15-18 | scenario NPV, cost overrun, benefit shortfall and hard gates | Stage, hold or approve investment. |
Exercise 1: Present Value of Annual Savings
A retrofit saves:
per year for five years. Use:
Find present value of savings.
Solution
Present value:
Engineering Comment
Savings should be traceable to measured or validated technical mechanisms.
Plausibility Check
Five undiscounted years are 160000, so present value below that is expected.
Exercise 2: Present Value of Residual Value
Residual value in year 5 is:
Use:
Find present value.
Solution
Present value:
Engineering Comment
Residual value should be supported by resale, reuse or salvage evidence.
Plausibility Check
The future amount is discounted to about two thirds.
Exercise 3: Net Present Value
Initial cost is:
Use:
Find NPV.
Solution
NPV:
Engineering Comment
The project is positive under the stated assumptions. Approval should still check whether savings evidence is strong enough.
Plausibility Check
Savings plus residual exceed initial cost by about eighteen thousand.
Exercise 4: NPV Margin Ratio
NPV is:
Initial cost is:
Find NPV margin as percent of initial cost.
Solution
Margin:
Engineering Comment
A fifteen percent margin is useful, but not immune to benefit shortfall or cost overrun.
Plausibility Check
Eighteen thousand is about fifteen percent of one hundred twenty thousand.
Exercise 5: NPV with Higher Initial Cost
If initial cost rises to:
while present benefits remain:
find revised NPV.
Solution
Revised NPV:
Engineering Comment
The project remains positive but becomes marginal. Cost control becomes a release gate.
Plausibility Check
Increasing cost by 15000 reduces the original 18011 NPV to about 3000.
Exercise 6: Simple Payback
Project cost is:
Annual saving:
Find simple payback.
Solution
Simple payback:
Engineering Comment
Simple payback ignores discounting and all benefits after payback.
Plausibility Check
Three years gives 85500 recovered; a bit more than three years is needed.
Exercise 7: Discounted Payback
Discounted cumulative savings through year 3 are:
Initial cost is:
Year 4 discounted saving is:
Estimate discounted payback.
Solution
Remaining after year 3:
Interpolated payback:
Engineering Comment
Discounted payback is longer than simple payback because future savings are worth less.
Plausibility Check
The remaining amount is slightly larger than year 4 discounted savings, so payback is just beyond year 4.
Exercise 8: NPV at MARR
A project costs:
and returns:
per year for five years. Use:
Find NPV at MARR.
Solution
NPV:
Engineering Comment
Positive NPV at MARR means the project exceeds the required return under this cash-flow model.
Plausibility Check
Discounted benefits are slightly above one hundred thousand, so NPV is positive but modest.
Exercise 9: IRR Interpolation
At 12\%, NPV is:
At 13\%, NPV is:
Estimate IRR by linear interpolation.
Solution
IRR:
Engineering Comment
IRR is above a 10\% MARR, but NPV is still the better value measure.
Plausibility Check
The sign changes between 12\% and 13\%, so IRR must lie between them.
Exercise 10: Profitability Index
Project A costs:
and has present benefits:
Find profitability index.
Solution
Profitability index:
Engineering Comment
PI helps under capital rationing but does not measure total dollars of value alone.
Plausibility Check
Benefits are thirty-eight percent above cost, so PI is 1.38.
Exercise 11: PI Ranking
Projects have:
| Project | Cost | PV benefits |
|---|---|---|
| A | 100000 | 138000 |
| B | 75000 | 96000 |
| C | 60000 | 84000 |
Rank by PI.
Solution
Compute:
Ranking:
Engineering Comment
Ranking by PI can favor smaller projects. Check absolute NPV and strategic constraints.
Plausibility Check
C has the highest benefit per dollar.
Exercise 12: Capital Budget Selection
Budget is:
Project costs and NPVs are:
| Project | Cost | NPV |
|---|---|---|
| A | 100000 | 38000 |
| B | 75000 | 21000 |
| C | 60000 | 24000 |
Choose the combination with highest NPV within budget.
Solution
Feasible combinations:
Choose A and C.
Engineering Comment
Capital rationing is a portfolio decision. Dependencies and resource limits should also be checked.
Plausibility Check
A plus C uses the full budget and has higher NPV than B plus C.
Exercise 13: Energy Price Threshold
Extra capital cost is:
Energy saving is:
Maintenance saving is:
Find electricity price for four-year simple payback.
Solution
Required annual saving:
Energy saving needed:
Price:
Engineering Comment
The threshold should be compared with tariff structure and operating profile.
Plausibility Check
Maintenance covers part of the needed saving, leaving about 7250 for energy.
Exercise 14: Minimum Annual Saving for NPV
A project costs:
and lasts six years. Use:
Find annual saving needed for zero NPV.
Solution
Set:
Solve:
Engineering Comment
This is the break-even annual benefit. Approval should require margin above it.
Plausibility Check
Six-year undiscounted average would be 30000; discounting raises the required annual saving.
Exercise 15: Scenario NPV
Base NPV is:
Benefit shortfall reduces present benefits by:
Find downside NPV.
Solution
Downside NPV:
Engineering Comment
The project is vulnerable to benefit shortfall. A pilot or staged approval may be appropriate.
Plausibility Check
The shortfall exceeds the base NPV, so downside NPV is negative.
Exercise 16: Cost Overrun Tolerance
Base NPV is:
Find maximum initial cost overrun before NPV reaches zero.
Solution
Maximum overrun equals the NPV margin:
Engineering Comment
If expected cost uncertainty is larger than this margin, approval should require contingency or redesign.
Plausibility Check
Every extra dollar of initial cost reduces NPV by one dollar.
Exercise 17: Benefit Realization Gate
Approved annual saving is:
Measured first-year saving is:
The gate requires at least 90\% of approved saving. Check.
Solution
Realization:
The gate fails:
Engineering Comment
Post-audit evidence matters. Under-realized benefits should feed future approval assumptions.
Plausibility Check
The measured saving is about 4500 below target, so realization below ninety percent is plausible.
Exercise 18: Investment Approval Gate
An investment package has:
| Gate | Requirement | Current result |
|---|---|---|
| NPV | positive | 18011 |
| discounted payback | at most 4 years | 4.03 years |
| downside scenario | nonnegative | -3989 |
| benefit evidence | at least 90\% realized | 85.9\% |
Decide whether to release.
Solution
NPV passes, but payback, downside scenario and benefit evidence fail:
The package should not receive unrestricted approval.
Engineering Comment
Positive base NPV is not enough when downside and measured benefit gates fail.
Plausibility Check
Multiple gates fail, so hold or stage approval is defensible.
Validation Package Checklist
A strong investment appraisal should check:
- whether cash-flow signs and timing are explicit;
- whether NPV, payback and IRR are interpreted for their proper purpose;
- whether MARR and discount factors match the decision basis;
- whether capital rationing uses feasible project combinations;
- whether threshold savings and cost-overrun tolerance are visible;
- whether scenario NPV checks downside exposure;
- whether measured benefits support approval assumptions;
- whether failed hard gates block unrestricted release.
Common Release Mistakes
Common mistakes include approving by simple payback alone, treating IRR as better than NPV for mutually exclusive alternatives, ignoring cost-overrun tolerance, using PI without budget feasibility, counting unvalidated benefits, omitting downside scenarios, and approving a project with positive base NPV while payback, downside or benefit-realization gates fail.