Exercise set
Waste-to-Energy Combustion, Efficiency, and Residuals Exercises
Solved waste-to-energy exercises for LHV, boiler input, net efficiency, auxiliary load, CHP, emissions, ash, residue volume and release gates.
These exercises focus on waste-to-energy combustion and residual controls. They cover heating value, boiler input, net electrical efficiency, auxiliary load, combined heat and power, availability, excess air, flue gas, reagent demand, particulate load, NOx, continuous monitoring, bottom ash, stabilization and residue disposal.
Assume simplified screening calculations unless an exercise states otherwise. Field release requires waste characterization, bunker controls, combustion records, boiler performance, turbine output, auxiliary load, air-pollution-control data, continuous emissions monitoring, ash testing and residue destination records.
Release Evidence Notes
Waste-to-energy evidence should distinguish gross energy input, gross electricity, net export and useful heat. A plant can produce power while still failing release if auxiliary load, downtime, emissions, ash quality or residue disposal is outside the allowed envelope.
Combustion evidence should state heating value basis, moisture, throughput, excess air, furnace temperature, residence time, burnout and upset periods. Averaged performance should not hide startup, shutdown or bypass events.
Residual evidence should include bottom ash, fly ash, reagent residues, metals stabilization, leachability testing and final disposal or beneficial-use destination.
Engineering Boundary Notes
These calculations do not replace permitted stack testing, combustion-control validation, ash hazardous-waste classification, grid interconnection studies or public-health risk assessment. They are screening calculations for release readiness and operating evidence.
Common Release Mistakes
- reporting gross generator output instead of net export after auxiliary load;
- using design heating value when current waste moisture has changed;
- treating air-emissions compliance as separate from the waste-to-energy release gate;
- ignoring ash mass and leachability when claiming diversion from landfill;
- averaging away startup, bypass, CEMS invalid hours or reagent-feed interruptions.
Scenario Map
| Scenario | Exercises | Primary check | Engineering decision |
|---|---|---|---|
| Energy conversion | 1, 2, 3, 4, 5, 6 | LHV, boiler input, net efficiency, auxiliary load, CHP and availability | Decide whether energy performance is credible. |
| Combustion and emissions | 7, 8, 9, 10, 11, 12 | excess air, flue gas, reagent, particulate, NOx and CEMS validity | Decide whether combustion controls support operation. |
| Residuals | 13, 14, 15, 16, 17 | ash mass, stabilization, landfill volume, bunker residence and evidence | Decide whether residual handling is controlled. |
| Release gate | 18 | all-of WTE release | Decide whether the package can close. |
Exercise 1: Waste Heating Value Blend
A waste feed is 70\% municipal solid waste at 9.5\ \text{MJ/kg} and 30\% commercial waste at 13.0\ \text{MJ/kg}. Estimate blended lower heating value.
Solution
Engineering Comment
The heating value basis should be tied to current waste characterization, not only historical design data.
Plausibility Check
The result lies between 9.5 and 13.0\ \text{MJ/kg}, closer to municipal waste because it is the larger fraction.
Exercise 2: Boiler Thermal Input
A WTE unit burns 18\ \text{t/h} of waste with LHV=10.55\ \text{MJ/kg}. Compute thermal input in MW.
Solution
Mass flow:
Thermal input:
Engineering Comment
This is fuel energy input. Boiler efficiency and auxiliary losses must be applied before claiming useful output.
Plausibility Check
Five kilograms per second at about 10\ \text{MJ/kg} gives about 50\ \text{MW}.
Exercise 3: Net Electrical Efficiency
Thermal input is 52.75\ \text{MW}_{th}. Gross generator output is 14.2\ \text{MW} and auxiliary load is 2.1\ \text{MW}. Compute net electrical efficiency.
Solution
Net export:
Net efficiency:
Engineering Comment
Net efficiency is the release-relevant electricity metric because fans, pumps, conveyors, reagent systems and controls consume real output.
Plausibility Check
WTE net electrical efficiency commonly sits well below a modern gas turbine, so a value near one quarter is plausible.
Exercise 4: Auxiliary Load Sensitivity
If auxiliary load rises from 2.1 to 3.0\ \text{MW} while gross output stays 14.2\ \text{MW}, compute the reduction in net export.
Solution
Old net export:
New net export:
Reduction:
Engineering Comment
Higher air-pollution-control pressure drop or cooling load can materially reduce net export even if combustion rate is unchanged.
Plausibility Check
The auxiliary load increased by 0.9\ \text{MW}, so net export falls by the same amount.
Exercise 5: Combined Heat and Power Efficiency
Net electrical export is 12.1\ \text{MW} and useful district heat is 18.0\ \text{MW}_{th}. Thermal input is 52.75\ \text{MW}_{th}. Compute useful CHP efficiency.
Solution
Engineering Comment
Useful heat must be actually delivered to a load. Dumped condenser heat should not be counted as CHP benefit.
Plausibility Check
Adding a large heat load roughly doubles useful output compared with electricity alone, so the efficiency rises materially.
Exercise 6: Availability-Adjusted Energy Export
Net export is 12.1\ \text{MW} when operating. Annual availability is 82\%. Estimate annual net export.
Solution
Engineering Comment
Availability must include forced outage, planned maintenance, grid curtailment and permit-driven shutdowns if they limit export.
Plausibility Check
A 12\ \text{MW} plant running all year would export about 105000\ \text{MWh}; 82\% availability brings it below 90000\ \text{MWh}.
Exercise 7: Excess Air Ratio
Stoichiometric combustion air is 6.2\ \text{kg air/kg waste}. Actual air feed is 9.0\ \text{kg air/kg waste}. Compute excess air.
Solution
Engineering Comment
Excess air supports burnout but increases flue-gas flow and can reduce boiler efficiency if too high.
Plausibility Check
Actual air is about one and a half times stoichiometric air, so excess air near 45\% is credible.
Exercise 8: Flue Gas Flow Screen
Waste feed is 18\ \text{t/h} and actual air feed is 9.0\ \text{kg air/kg waste}. Estimate air mass flow to the furnace.
Solution
Engineering Comment
Flue-gas flow drives induced-draft fan load, residence time and air-pollution-control sizing.
Plausibility Check
Combustion air is several times larger than waste mass flow, so tens of kilograms per second is reasonable.
Exercise 9: Acid Gas Reagent Demand
An acid-gas control system injects 1.8\ \text{kg} reagent per tonne of waste. Waste throughput is 420\ \text{t/d}. Compute reagent use.
Solution
Engineering Comment
Reagent feed evidence should be paired with inlet acid-gas load, outlet concentration and residue generation.
Plausibility Check
About two kilograms per tonne over a few hundred tonnes per day gives several hundred kilograms per day.
Exercise 10: Particulate Load to Baghouse
Flue gas flow is 160000\ \text{m}^3/\text{h} and particulate concentration entering the baghouse is 1.25\ \text{g/m}^3. Compute particulate mass loading.
Solution
Engineering Comment
The baghouse and ash-handling system must handle this load without blinding, hopper plugging or bypass.
Plausibility Check
One gram per cubic meter over a very large flow creates hundreds of kilograms per hour.
Exercise 11: NOx Compliance Margin
Measured NOx is 145\ \text{mg/Nm}^3. Permit limit is 180\ \text{mg/Nm}^3. Compute compliance margin.
Solution
Engineering Comment
The margin should be reviewed across load, waste composition, ammonia or urea feed and averaging period.
Plausibility Check
The plant is 35\ \text{mg/Nm}^3 below a 180\ \text{mg/Nm}^3 limit, roughly one fifth of the limit.
Exercise 12: CEMS Valid-Hours Check
A reporting month has 720 hours. The continuous emissions monitoring system has 681 valid hours. The valid-data target is 95\%. Determine whether the target is met.
Solution
The target is not met because:
Engineering Comment
Energy performance cannot close the release package if emissions data completeness fails.
Plausibility Check
The plant is short by a few hours: 0.95(720)=684 required hours.
Exercise 13: Bottom Ash Mass
Waste throughput is 420\ \text{t/d}. Bottom ash is 22\% of waste mass. Compute bottom ash production.
Solution
Engineering Comment
Bottom ash remains a major residual stream even when waste volume is reduced.
Plausibility Check
About one fifth of 420\ \text{t/d} is a little over 80\ \text{t/d}, so 92.4\ \text{t/d} is plausible.
Exercise 14: Ash Stabilization Margin
A treated fly ash sample has leachate lead of 3.2\ \text{mg/L}. The release criterion is 5.0\ \text{mg/L}. Compute margin.
Solution
Engineering Comment
The margin is useful only if sampling is representative of current reagent dose, waste composition and operating condition.
Plausibility Check
The result is comfortably below the criterion, leaving a little more than one third of the limit as margin.
Exercise 15: Residue Landfill Volume
Combined ash and residues are 110\ \text{t/d}. Compacted residue density is 1.15\ \text{t/m}^3. Compute daily landfill volume required.
Solution
Engineering Comment
WTE reduces raw waste volume, but it does not eliminate disposal planning for ash and air-pollution-control residues.
Plausibility Check
At density a little above one tonne per cubic meter, tonnes per day and cubic meters per day are similar.
Exercise 16: Waste Bunker Residence Time
The waste bunker contains 2100\ \text{t} of usable inventory. Furnace throughput is 420\ \text{t/d}. Compute residence time.
Solution
Engineering Comment
Bunker residence time affects odor, fire risk, crane mixing and ability to ride through collection interruptions.
Plausibility Check
At 420\ \text{t/d}, five days consumes 2100\ \text{t}.
Exercise 17: WTE Evidence Completion
A WTE release checklist has 12 required records: waste LHV, throughput, furnace temperature, excess air, gross output, auxiliary load, reagent feed, CEMS validity, NOx margin, particulate control, ash test and residue destination. Ten are complete. Compute completion.
Solution
Engineering Comment
The package is incomplete if missing records are emissions, ash or residue controls, even when energy output is documented.
Plausibility Check
Ten of twelve is five sixths, or about 83\%.
Exercise 18: WTE Release Gate
A release gate requires net electrical efficiency above 20\%, NOx margin above 10\%, CEMS valid hours at least 95\%, ash stabilization margin above 20\% and evidence completion above 90\%. Current values are 22.9\%, 19.4\%, 94.6\%, 36\% and 83.3\%. Decide release status.
Solution
Net efficiency passes, NOx margin passes and ash margin passes. CEMS validity and evidence completion fail:
Release status:
Engineering Comment
The plant may be operating well energetically, but the release package cannot close without emissions-data completeness and full residual evidence.
Plausibility Check
An all-of release gate fails when any mandatory monitoring or evidence threshold fails.
Validation Package Checklist
- Heating value, throughput, boiler input, gross output, auxiliary load and net export use the same operating window.
- Combustion evidence includes excess air, furnace conditions, CEMS validity, reagent feed and air-pollution-control status.
- Ash and residue records include mass, stabilization, leachability, storage and final destination.
- Release decisions preserve startup, shutdown, bypass, invalid data and residue exceptions instead of averaging them away.